You are here »» Home »» Elevators & Escalator »» Installation
Installation
We provide the complete spectrum of the Schindler products & services spanning from Escalators, moving walkways e.t.c if required
by a project Our Products are mainly Schindler products; we install elevators on new buildings or existing shafts. For many years
we have represented the above principals with a fully equipped Technical team fitted with the appropriate Test and Repair Equipment.
Schindler elevators are equipped with latest technology and also offer a wide range of extras.
SCHINDLER DIVISION PROFILE Select List of Major Projects Executed Government
& Parastatals
| BANK OF UGANDA
- KAMPALA |
| 3 Nos. |
Passenger Lifts |
1000kgs |
9 stops |
| 1 No. |
Passenger Lift |
1000kgs |
10 stops |
| 1 No. |
Cargo Lift |
1250kgs |
10 stops |
| 1 No. |
Bullion Lift |
1000kgs |
3 stops |
| BANK OF BARODA
- KAMPALA |
| 1 No. |
Passenger Lift |
800kgs |
6 stops |
| EAST
AFRICAN DEVELOPMENT BANK - KAMPALA |
| 2 Nos. |
Passenger Lifts |
1000kgs |
11
stops |
| COMMUNICATION HOUSE
- KAMPALA |
| 5 Nos. |
Passenger Lifts |
1250kgs |
16 stops |
| CONRAD PLAZA -
KAMPALA |
| 2 Nos. |
Passenger Lifts |
630Kgs |
12 stops |
| KING FAHD PLAZA
- KAMPALA |
| 2 Nos. |
Passenger Lifts |
1000kgs |
12 stops |
| DIAMOND TRUST
- KAMPALA |
| 2 Nos. |
Passenger lifts |
800kgs |
14 stops |
| IPS BUILDING
- KAMPALA |
2
Nos. |
Passenger Lifts |
1000kgs |
10 stops |
| BANK OF UGANDA
- MBARARA |
| 1 |
Bullion Lift |
1000kgs |
2 stops s |
| CRESTED TOWERS
- KAMPALA |
| 4 No. |
Passenger Lifts |
1250
kgs |
20 stops |
| 4 No. |
Passenger Lifts |
1250 kgs |
12 stops |
| BANK OF UGANDA
- GULU |
| 1 No. |
Bullion Lift |
1000kgs |
3 stops |
| MINISTRY OF EDUCATION
& SPORTS - KAMPALA |
| 1 No. |
Passenger Lift |
1000kgs |
10 stops |
| 1 No. |
Passenger Lift |
1000kgs |
9 stops |
| UTC COMMERCIAL
CENTRE, KIGALI |
| 1 No. |
Passenger Lift |
630kgs |
4 stops |
|